Work under way to carry out barrier improvements on A90
Work began this week to install new safety barriers on a section of the A90, with the project due to continue into next month.
Amey is undertaking the road safety improvements between Finavon and Brechin on behalf of Transport Scotland


The new vehicle safety barriers are being installed on the nearside lane of both the north and southbound carriageways, with work due to be completed on Friday, February 20.
Work is taking place between the on slip to the dual carriageway at Peggy Scott’s restaurant and the A935 St Ann’s junction at Brechin.
To ensure the safety of roadworkers and motorists, the work will be undertaken under 24/7 lane one restrictions on each carriageway at rolling locations as follows:-
Monday, January 26 to Tuesday, February 3 (weekdays only): Lane 1 restriction southbound between St Ann’s Interchange and Balnabriech Junction.
Tuesday, February 3 to Friday, February 6: Lane 1 restriction southbound between approx. 1.4km north of Finavon and Finavon itself.
Monday, February 9 to Tuesday, February 24 (weekdays only): Lane 1 restriction northbound between Finavon and Waterston Road. A 50mph speed limit will be in place 24/7 at each location while work is taking place due to the need for a temporary vehicle restraint system.
The improvements will benefit more than 21,500 vehicles which use this route each day. A free Road Work Alerts service is available from the Amey website.