Substation appeal to be dealt with by Holyrood

Scottish ministers have taken control of a planning appeal against Angus Council’s refusal of a huge electricity substation near Tealing.

SSEN Transmission’s 400/275kV Emmock proposal would be sited close to the A90, just north of Dundee.

​The application for the rural site will now be considered by Scottish ministers. (Pic: Google Maps)​placeholder image
​The application for the rural site will now be considered by Scottish ministers. (Pic: Google Maps)​

However, Angus councillors rejected the application for the scheme last December.

Planning officials had recommended conditional approval, but elected members voted overwhelmingly against it.

Campaigners said Tealing is being swamped by industrialisation which will cause “catastrophic harm”.

And the Emmock proposal attracted the largest ever response to a single Angus planning application with around 1700 objections.

The 22-bay substation would cover an area the size of around 28 football pitches on a site of around 200 acres.

In the latest development, the Scottish Government has announced SSEN’s appeal against the substation refusal will now rest with the top level at Holyrood.

They say that is because the application raises matters of “national importance”.

The appeal had been allocated to a reporter in the Scottish Government’s planning and environmental appeals division. Under the Town and Country Planning (Scotland) Act 1997, ministers will now decide its outcome.

A recall notice states: “Scottish Ministers have given this direction as it is considered it raises matters of national importance in the context of National Planning Framework 4 expectations for strategic renewable electricity generation and transmission Infrastructure.”

The Emmock project is part of SSEN’s huge Pathway to 2030 nationwide infrastructure upgrade. This includes the planned Kintore to Tealing 400kV overhead line project.

A public inquiry into the ‘super-pylons’ scheme will be held this summer.

The project involves new pylons, averaging 57 metres in height, being erected through more than 60 miles of Aberdeenshire and Angus countryside.

However, the scheme was branded “an act of vandalism on a colossal scale”. Councillors contradicted the advice of the head of planning to lodge an objection with the Scottish Government’s energy consents unit.