Multi-million pound project to tackle flooding problem in Montrose

The first stage of a multi-million pound project to upgrade part of Montrose’s waste water network and tackle a flooding problem is due to get under way next week.

Scottish Water is carrying out upgrading of the sewerage network in the Borrowfield area in a bid to prevent sewer flooding and protect the local environment.

​A storm tank will be constructed beneath Borrowfield Park.placeholder image
​A storm tank will be constructed beneath Borrowfield Park.

The project at Borrowfield Park and on Aulton Way, Newmanswalls Avenue and Newhame Road is due to start this Monday (August 24) with the setting up of the site compound in Borrowfield Park.

It is the culmination of years of work between the water authority and local stakeholders to investigate and address decades of flooding problems in the area. And the construction work is set to be extensive.

A Scottish Water spokesperson said: “Following extensive survey work, we have identified an investment proposal which would significantly reduce the risk of sewer flooding in the area, with allowance for the impact of more frequent intense rainstorms.

“This project will involve the installation of a new pipeline as well as the construction of a new underground storm overflow tank. Construction activity is required across a significant area. The underground storage tank will measure 25 metres wide, 9.5 metres deep and have the capacity to store up to 3.5 million litres - more than an Olympic-sized swimming pool.”

New sewers will be constructed in Aulton Way, Newmanswalls Avenue and Newhame Road, during which time roadworks will be required to allow the work to be carried out safely.

The spokesperson added: “Scottish Water is responsible for the sewer network across the country; and we have confirmed that a large part of the flooding problem has been caused by a lack of capacity in the local sewers during heavy rainstorms, which are becoming more frequent under the influence of climate change.

“Customers in the area have had their streets flooded, with damage to cars and gardens – and ongoing worry during weather conditions when flooding may occur. The project will significantly reduce the risk of sewer flooding by increasing the capacity of the network and providing extra storage during heavy rainfall.”